Greater Shepparton City Council has advised changes to upcoming road works along Casey Street in Tatura. The roadworks will now be undertaken in two stages.
Stage 1 asphalting works on Casey Street, between Fraser and Francis Street, will now take place from Monday, June 23 to Thursday, June 26.
Stage 2 involves asphalting works near the roundabout of Casey and Brown Streets, which will take place on Friday, June 27.
The road will remain open during the first stage with traffic management in place between 7.30am and 5.30pm. However, the construction area at Casey and Albert Streets will close Friday for the second stage, with no through traffic permitted between 7.30am and 5.30pm.
Pedestrian access to the surrounding footpaths will remain available during the works.