CONSTRUCTION continues at Vibert Reserve Pavilion. Crow Constructions have completed the new maintenance entrance and have relocated the pump system infrastructure to the new yard beside the cricket nets.
The tanks have been filled and the system commissioned with irrigation to Vibert Reserve and McGuire ovals are now operational. Building fencing is the next step to finish off the irrigation yard.
With demolition completed, work has moved in preparation for construction of the concrete slabs. The contractor has been progressing work on the western extension of the building constructing sub-sewer and footings, including inspections. The footings for the eastern extension have also been prepared, inspected, and poured. Minor electrical works have also been completed.
Reminder – parking at the reserve is closed but sporting fields remain open. Take care when visiting the area that you observe any exclusion zones and traffic management. Bookings to use the fields can be made by contacting Council’s Parks, Sport and Recreation Department on 03 5832 9700.