Coming along nicely

READY FOR TERM ONE 2024...After months of land preparation and clearing, a former paddock now hosts the foundation of the new All Saints Anglican School. Next month the school will start to 'grow' from the ground as pre-cast walls for the administration building are raised into place. The administration building slab has been poured, with the junior school building slab to follow in the coming weeks. Photo: Supplied

BUILDINGS works are progressing rapidly on the site of the eagerly anticipated All Saints Anglican School.

After months of land preparation and clearing, the former paddock now hosts the foundation of a new school.

Next month, the school will start to ‘grow’ from the ground as pre-cast walls for the administration building are raised into place.

The administration building slab has been poured, with the junior school building slab to follow in the coming weeks. Further building works in June include the commencement of northern entry pedestrian footpaths, additional ground floor slabs and the installation of underground services.

The School will open for Term 1 in 2024.

READY FOR TERM ONE 2024…After months of land preparation and clearing, a former paddock now hosts the foundation of the new All Saints Anglican School. Next month the school will start to ‘grow’ from the ground as pre-cast walls for the administration building are raised into place. The administration building slab has been poured, with the junior school building slab to follow in the coming weeks. Photo: Supplied